Astana Arena — Fire Suppression System
Restoration with replacement of outdated automation: new control cabinets, controllers, protection algorithms, and integration with the fire alarm system.
For the Astana Arena sports complex, Atlas Scada carried out the restoration of the fire suppression system with a full replacement of the outdated control automation. The objective was to bring the system back to working order, increase the reliability of automatic control, and ensure correct interaction between all fire suppression components.
What the survey revealed
- Faulty operation of the fire suppression control cabinets.
- Absence of redundancy and protection algorithms.
- Failures in transmitting control and monitoring signals.
- Inability to fully test the system in automatic mode.
Technical solutions
- Restoration of the automatic and manual start logic.
- Control of the fire suppression pump group.
- Monitoring of valves, pressure and level sensors.
- Emergency and protection algorithms.
- Integration with the fire alarm system.
What was done
- Faulty and obsolete control components were dismantled.
- New automation cabinets were installed: fire suppression control controllers, I/O modules, motor-starting and protection gear for the pump units, and actuator monitoring devices.
- Installation was performed in stages, without disrupting the facility's operation and in line with fire safety requirements.
- Controllers were programmed and commissioning was carried out, verifying automatic start-up, manual modes, interaction with the fire alarm system, and the operation of protections and interlocks.
Result
- Full operability of the fire suppression system was restored.
- Reliable automatic control of the pump group was ensured.
- Correct interaction with the fire alarm system was established.
- The facility's level of fire safety was raised.
Project duration — 7 days.

Quryq Port — Marine Firefighting System
Restoration of a 2×140 kW pump station, zoned automatic suppression, foam fire suppression for the railway tracks, dispatch integration with the fire brigade, and redundant control.

Prosecutor General's Office of the RK — heating substations
Reconstruction of heating substations with a full replacement of automation: automatic control of coolant temperature, protective algorithms, and connection to dispatch monitoring.

Green Mall Shopping Center — Fire Suppression
Installation and automation of the shopping center's fire suppression systems: pump units, control cabinets, automatic standby switchover, motor protection, commissioning.