At the Anvar store, Atlas Scada carried out commissioning of the heat substation installed in the retail facility's building.
Initial conditions
The heat substation had been installed but not put into operating mode, and it required commissioning to ensure correct and safe operation.
What we did
- Verified the correctness of the heat substation equipment installation.
- Checked the connection of the instrumentation and measuring devices.
- Verified the operation of the actuators.
- Tuned the operating parameters of the heat substation.
- Tested the system across operating modes.
Performance verification
The heat substation was started up and its operating stability under load was verified; all parameters were brought into compliance with the design requirements and the building's operating conditions.
Result
The heat substation was put into operation and handed over to the client in working condition. Reliable and correct operation of the facility's heat supply system was ensured. Project duration — 3 days.

Quryq Port — Marine Firefighting System
Restoration of a 2×140 kW pump station, zoned automatic suppression, foam fire suppression for the railway tracks, dispatch integration with the fire brigade, and redundant control.

Prosecutor General's Office of the RK — heating substations
Reconstruction of heating substations with a full replacement of automation: automatic control of coolant temperature, protective algorithms, and connection to dispatch monitoring.

Astana Arena — Fire Suppression System
Restoration with replacement of outdated automation: new control cabinets, controllers, protection algorithms, and integration with the fire alarm system.